Question 90
Who creates the Sprint Goal?
(choose the best answer)
- A The Scrum Master
- B The Scrum Team
- C The Product Owner
- D The Developers
- E Stakeholders
Reveal correct answer
Correct answer: B
Explanation
The Scrum Team is responsible for defining the Sprint Goal during Sprint Planning. The Sprint Goal is a short, concise objective that provides guidance and focus for the Developers during the Sprint. It is determined collaboratively by the Scrum Team, which includes the Product Owner, the Scrum Master, and the Developers. The Sprint Goal reflects the purpose of the Sprint and serves as a unifying factor for the team to align their work and make decisions during the Sprint.Discussion