Professional Scrum Master I PSM I · Free Practice Question Easy

Question 83

Which statement best describes the Sprint Backlog resulting from the Sprint Planning?

(choose the best answer)

  • A Contains tasks lasting at most one day
  • B It contains Product Backlog items selected by the Product Owner
  • C It contains all the work to be delivered during the Sprint
  • D It is the Scrum Team's plan for the Sprint
  • E Every task has a designated owner
Reveal correct answer

Correct answer: D

Explanation

The output of the Sprint Planning is the first version of the Sprint Backlog, created by the collaborative work of the entire Scrum Team.