Professional Scrum Master I PSM I · Free Practice Question Easy
Question 72
What is the recommended action for the Product Owner between the end of the current Sprint and the start of the next Sprint?
(choose the best answer)
- A Refine the Product Backlog.
- B Collaborate with the Developer on testing the current Sprint's Increment.
- C Conduct a review of the project's progress with stakeholders.
- D There is no gap. A new Sprint starts immediately after the conclusion of the previous Sprint.
Reveal correct answer
Correct answer: D
Explanation
According to the Scrum Guide, there is no activity gap between Sprints. As soon as one Sprint concludes, the next Sprint starts immediately. This ensures a continuous flow of work and allows the Scrum Team to maintain a sustainable pace.Discussion