Professional Scrum Master I PSM I · Free Practice Question Easy

Question 66

Who has the authority to cancel the Sprint?

(choose the best answer)

  • A The Key Stakeholders
  • B The Scrum Master
  • C The Developers
  • D The Product Owner
  • E The Product Owner and the Scrum Master
Reveal correct answer

Correct answer: D

Explanation

Only the Product Owner has the authority to cancel the Sprint, although he or she may do so under influence from the stakeholders, the Developers, or the Scrum Master.