Professional Scrum Master I PSM I · Free Practice Question Easy

Question 47

Who must participate in the Daily Scrum?

(Select the best answer)

  • A The Developers.
  • B The Scrum Master.
  • C The Product Owner.
  • D The Scrum Team.
Reveal correct answer

Correct answer: A

Explanation

All the Developers of the Scrum Team must be present at the Daily Scrum since it is an event for them to inspect progress toward the Sprint Goal and adapt the Sprint Backlog as necessary, adjusting the upcoming planned work.