Professional Scrum Master I PSM I · Free Practice Question Easy

Question 24

When is the Sprint over?

(Select the best answer)

  • A When the timeboxed duration is over
  • B When the Product Owner announces the end of the Sprint
  • C When the Scrum Master announces the end of the Sprint
  • D When the Sprint Backlog tasks are done
Reveal correct answer

Correct answer: A

Explanation

It's a simple question: you need to know what timeboxing means, and that Sprints are timeboxed. Other than the normal ends of Sprints, the Product Owner also has the authority to cancel a Sprint.