Professional Scrum Master I PSM I · Free Practice Question Easy
Question 24
When is the Sprint over?
(Select the best answer)
- A When the timeboxed duration is over
- B When the Product Owner announces the end of the Sprint
- C When the Scrum Master announces the end of the Sprint
- D When the Sprint Backlog tasks are done
Reveal correct answer
Correct answer: A
Explanation
It's a simple question: you need to know what timeboxing means, and that Sprints are timeboxed. Other than the normal ends of Sprints, the Product Owner also has the authority to cancel a Sprint.Discussion