Professional Scrum Master I PSM I · Free Practice Question Easy

Question 17

True or False: Sprint Review is not a formal meeting.
  • A TRUE
  • B FALSE
Reveal correct answer

Correct answer: A

Explanation

Scrum prescribes four formal events for inspection and adaptation: Sprint Planning, Daily Scrum, Sprint Review, and Sprint Retrospective. Be alert: the word formal is used in two distinct ways! First, the four formal events for inspection and adaptation, which means a formal opportunity. A formal meeting means a meeting where people approve something and exchange signatures. In that sense, none of the events are formal meetings. The Sprint Review meeting is informal, not a status meeting, and the Increment presentation is intended to elicit feedback and foster collaboration.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need