Prince2 7 Foundation · Free Practice Question Easy

Question 27

Which aspect of project performance must be managed in order to have a clear understanding of whether a given project is affordable for an organization?
  • A Timescale
  • B Scope
  • C Risk
  • D Costs
Reveal correct answer

Correct answer: D

Explanation

OBJ 1.1: There are six variables involved in any project: costs, scope, timescales, quality, benefits, and risks. Cost defines how many monetary resources are required for a given project. The project has to be affordable and, though we may start out with a particular budget in mind, there will be many factors that can lead to overspending and, perhaps, some opportunities to cut costs.