Prince2 7 Foundation · Free Practice Question Easy
Question 26
Which of the following is a purpose of the starting up a project process?
- A To ensure that the prerequisites for initiating the project are in place
- B To establish whether the project plan can meet the required target dates
- C To assemble the project initiation documentation so the project can be initiated
- D To confirm to corporate, program management, or the customer that quality expectations will be met
Reveal correct answer
Correct answer: A
Explanation
OBJ 4.1: The purpose of the starting up a project process is to ensure that the prerequisites for initiating a project are in place by answering the question: Do we have a viable and worthwhile project? The decision to start the project must be explicit; the activities from starting up a project happen before this decision. While the customer's quality expectations are captured and documented in the project product description during the starting up a project process, there is no confirmation that these will be met at this point in time as they are a target objective.Discussion