Prince2 7 Foundation · Free Practice Question Easy

Question 26

Which of the following is a purpose of the starting up a project process?
  • A To ensure that the prerequisites for initiating the project are in place
  • B To establish whether the project plan can meet the required target dates
  • C To assemble the project initiation documentation so the project can be initiated
  • D To confirm to corporate, program management, or the customer that quality expectations will be met
Reveal correct answer

Correct answer: A

Explanation

OBJ 4.1: The purpose of the starting up a project process is to ensure that the prerequisites for initiating a project are in place by answering the question: Do we have a viable and worthwhile project? The decision to start the project must be explicit; the activities from starting up a project happen before this decision. While the customer's quality expectations are captured and documented in the project product description during the starting up a project process, there is no confirmation that these will be met at this point in time as they are a target objective.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need