Question 22
Which type of issue should be raised if a new product is required after a team has started work?
- A A request for change
- B An off-specification
- C A problem
- D A concern
Reveal correct answer
Correct answer: A
Explanation
OBJ 3.6.3: A request for change is a type of issue that is a proposal for a change to a baseline. The product description should have been baselined before work began. Therefore, this is a request for change to a baselined product.Discussion