Prince2 7 Foundation · Free Practice Question Easy
Question 10
Which of the following is an objective of the controlling a stage process?
- A To ensure that there is authority to initiate the project
- B To ensure that all benefits have been achieved
- C To act as a link between those managing the project and those creating products
- D To capture the customer's quality expectations
Reveal correct answer
Correct answer: C
Explanation
OBJ 4.2: The objective of the controlling a stage process is to act as a link between those managing the project and those creating products. The purpose of the controlling a stage process is to assign work to be done, monitor such work, deal with issues, report progress to the project board, and take corrective actions to ensure that the management stage remains within tolerance.Discussion