Prince2 7 Foundation · Free Practice Question Easy

Question 8

Which of the following is a part of the change theme?
  • A To identify, assess and control uncertainty within the project
  • B To establish a coding system for all components of the project's products
  • C To define the means of delivering the products
  • D To produce a benefits management approach
Reveal correct answer

Correct answer: B

Explanation

OBJ 3.6.1: The identification of project products involves configuration management, which is a part of the change theme. The purpose of the change theme is to identify, assess, and control any potential and approved changes to the project baselines.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need