Prince2 7 Foundation · Free Practice Question Easy
Question 6
Who is responsible for documenting any tailoring of the project plan?
- A The executive
- B The project manager
- C A team manager
- D Project support
Reveal correct answer
Correct answer: B
Explanation
OBJ 2.2: The project manager is responsible for identifying and documenting the level of tailoring for the project. Regardless of the document being considered, any tailoring must be documented by the project manager in the project initiation documentation (PID).Discussion