Question 19

What is COBIT design process phase called when inherent priority conflicts are resolved?

  • A

    Determine the initial scope of the governance system

  • B

    Refine the scope of the governance system

  • C

    Conclude the governance system design

Reveal correct answer

Correct answer: C