Certified Systems Engineering Professional Csep · Free Practice Question Easy
Question 30
[ID-2063] Which of the following is an activity of the portfolio management process?
-
A
Analyze risks.
-
B
Control individual projects.
-
C
Activate projects.
-
D
Terminate projects.
Reveal correct answer
Correct answer: D
A.
This is done by the risk assessment process. See INCOSE SE Handbook 5th Ed. section 2.3.4.4, p.82
B.
This is done by the project assessment and control process. See INCOSE SE Handbook 5th Ed. section 2.3.4.2, p.76
C.
The portfolio management process is the one responsible for authorizing project execution, but the initiation is done by the project planning process. See INCOSE SE Handbook 5th Ed. section 2.3.4.1, p.71.
D.
The portfolio management process is the one responsible for authorizing the initiation of projects and also for terminating them. See INCOSE SE Handbook 5th Ed. section 2.3.3.3, p.58.