PMI Agile Certified Practitioner PMI ACP · Free Practice Question Easy

Question 75

Amara’s agile team is estimating story points. Which of the following is it essential to include?
  • A Meeting times
  • B Vacations and sick days
  • C Testing and refactoring
  • D Server backup time
Reveal correct answer

Correct answer: C

Explanation

Story point estimates need to include all known activities required to complete the story, including testing and refactoring, complexity level, risk level, etc. Instead of factoring a certain fudge factor, including all activities proves to be more accurate. The other answers are incorrect because vacations and sick days shouldn’t be considered in an estimate, only known activities should be considered; meeting times are not included in story estimates; server backup times are also not included as part of the story point estimating.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.