Question 74

Sarah uses Sprint Retrospectives to make her team more effective. The way that she is most likely to do this is:
  • A To reflect on increasing customer value and effectiveness, through retrospection and adjustment in behaviors going forward
  • B To focus on doing a retrospective only as part of the product planning cycle, not as a specific part of the sprint cycles
  • C At the beginning of each cycle, she shows the development team a demo of what has been built to date
  • D At the end of every major release to production they assess each member of the team
Reveal correct answer

Correct answer: A

Explanation

1 is correct because sprint retrospectives are performed to determine areas of improvement and to allow the team to make those adjustments in the future. 2, 3, and 4 are incorrect. 2 is incorrect because the retrospective could be during an iteration or release. 3 and 4 are incorrect choices because Sarah does not need to have a demonstration at the beginning of each cycle focused on developers.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need