Question 70

As they learn more about how to complete the project, Fallon and her team expect that the plans made at the beginning of the project will change throughout its progression. In practice, this is implemented by:
  • A Once the first changes are requested, the full planning process can be repeated
  • B At each regular meeting, ask for suggested changes from all team members
  • C While planning, expect changes are coming, welcome the changes when they do come, and adjust the plan accordingly
  • D Because you know the project will change, never estimate the release date
Reveal correct answer

Correct answer: C

Explanation

The correct answer is to expect changes while planning. Changes should not only be expected but welcomed; when they happen, they should influence the plan itself. The other responses are incorrect. When the first change is requested, nothing of significance should occur; it all depends on the nature of the change. Additionally, a change does not imply that you should never estimate a release date; there’s no reason to ask for change suggestions at each meeting.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need