PMI Agile Certified Practitioner PMI ACP · Free Practice Question Easy
Question 66
Crystal is working with an agile team that is developing and delivering a software solution to her company’s HR group. Throughout the project, many MVP (minimum viable product) releases are scheduled. Why is this a good idea?
- A To enable the business to begin to get value from the project before the project ending
- B To show the progress being made by the development team
- C To enable the users to test the product for the development team
- D To shorten the duration of the project
Reveal correct answer
Correct answer: A
Explanation
The correct answer is to enable the business to begin to get value from the project before the project’s end. While the team is developing the remaining functionality, incremental releases may allow for some ROI. The other responses are incorrect. The purpose of releasing MVPs is to deliver value, not to show the project’s progress. The product, in this case, software, should already be thoroughly tested and functional before being released to users. Finally, the duration of the project will not be shortened by releasing MVPs; the MVPs are defined in the project life cycle.Discussion