Question 64

To welcome and incorporate expected changes in her team’s project, Alisha has created an agile approach. Her best approach is what?
  • A To incorporate quick changes, Alisha holds standup change request meetings every day
  • B All changes are added to the Sprint Backlog by Alisha
  • C Alisha notifies her company of the new items and guarantees, along with the sponsor, to respond within 24 hours to all new change control requests
  • D As changes are discovered, Alisha makes a note of the new work required and places the information into a backlog where the entire team may access it in the future
Reveal correct answer

Correct answer: D

Explanation

The correct answer is to make notes as changes are discovered, and ensure the team has access to them. This is an appropriate approach to handling change: making the changes highly visible; discussing the changes as a team; putting the change request into the backlog for future use. The other responses are incorrect because new items go into the product backlog, not the spring backlog; attempting to enforce a formal and rigid change control process, like the guarantee to respond to requests in less than 24 hours, is not the best approach; an appropriate approach to change management involves more than simply meeting with the client.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.