PMI Agile Certified Practitioner PMI ACP · Free Practice Question Easy

Question 54

Marilyn is moving to a small private room near her team for the latter part of the afternoon to focus on a tough part of her development work in a quiet environment. Her Scrum Master tells her:
  • A That she should not be isolating herself from the rest of the team like this
  • B That she is welcome to use this as her space throughout the project if she'd like
  • C Nothing, as they have intentionally set up the team's cave for this purpose
  • D That the team's cave is only to be used for private conversations
Reveal correct answer

Correct answer: C

Explanation

Caves are set up for short work periods when a team member needs isolation for a short time, whether to work quietly, have a confidential conversation, or a private meeting.The other answers are inaccurate descriptions of the use of a cave. It is permissible to use a cave for quiet time for short periods. There is no requirement that it be just for private conversations. It should also not be overused.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need