PMI Agile Certified Practitioner PMI ACP · Free Practice Question Medium
Question 46
Danny’s team area includes a cave. The cave has been in demand with everyone needing to use it not being able to due to lack of space in the small room. The best solution for resolving this problem is:
- A Placing smaller furniture in the room to enable more capacity
- B Expanding the size of the cave
- C Facilitating a team discussion around the creation of quiet hours where the delivery team is not interrupted by others
- D Creating a sign-up schedule posted on the team's information radiator
Reveal correct answer
Correct answer: C
Explanation
The best choice is to approach the cause of this issue, which is that the team is avoiding the team’s primary area due to too many interruptions in the common area. Engaging the team about the root problem will help them come up with solutions (such as quiet hours) to help solve the challenge.The other solutions are not as good as addressing the root cause. The team's area should primarily be used except for the occasional need to retreat, so expanding the size or adding furniture would not be addressing the root cause. Agile wouldn't encourage the overhead or formality of an extra schedule.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.