PMI Agile Certified Practitioner PMI ACP · Free Practice Question Easy

Question 9

There are many different methods of testing software or product deliverables, and each one has its own strengths and weaknesses. When should the team choose the method of testing?
  • A When the first iteration is complete
  • B Before the product is developed
  • C When a deliverable is available for testing
  • D At the end of the project
Reveal correct answer

Correct answer: B

Explanation

Before the product is developed is the correct answer. You are more likely to end up with tests for the bulk of the work if the acceptance tests are created before the development of deliverables.The other responses are incorrect. When you determine the testing method after the project has started, it means you are trying to fit the developed product into a test scenario.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need