Question 5
To keep a project on track, it’s good practice to minimize waste. To maximize a project’s value, which of the following could be eliminated?
- A Timpani
- B Daily meetings
- C Sprint reviews
- D Unnecessary features
- E Testing
- F Violin
Reveal correct answer
Correct answer: D
Explanation
Unnecessary features is the correct answer as these are part of waste in a project. In addition, value can be maximized by eliminating partially done work, delays, extra processes, and features, task switching, waiting, moving information or a deliverable, defects, and handoffs.Daily meetings, testing, and Sprint reviews are incorrect because they represent just a few of the activities required for a successful project, and are not necessarily wasteful.Discussion