PMI Agile Certified Practitioner PMI ACP · Free Practice Question Easy
Question 1
As an Agile project manager, Lynn wants her team to be which of the following?
- A Have total dependency on the product backlog
- B Self-managed and self-organized
- C Servant leaders and self-organized
- D Have total dependency on the project plans
Reveal correct answer
Correct answer: B
Explanation
The correct answer is self-managed and self-organized. All Agile teams are self-managed and self-organized, regardless of the specific framework.Discussion