Certified Associate In Project Management CAPM · Free Practice Question Easy

Question 81

There’s a risk that a new law will cause your project to fail. What risk response can you use for this possible law?
  • A Mitigation
  • B Transference
  • C Exploit
  • D Acceptance
Reveal correct answer

Correct answer: D

Explanation

The only response you can do is to accept the risk. 1 is incorrect because you cannot mitigate the risk. 2 is incorrect because you cannot transfer the risk. 3 is incorrect because you cannot accept the risk.