Certified Associate In Project Management CAPM · Free Practice Question Easy

Question 70

You are the project manager for your organization. You have just been assigned a new project with a predetermined budget of $250,000. This is an example of which one of the following?
  • A Constraint
  • B Assumption
  • C Expert judgment
  • D Functional structure
Reveal correct answer

Correct answer: A

Explanation

A predetermined budget is a project constraint. 2 is incorrect because this is not an example of an assumption. 3 is incorrect because this is not an expert judgment. 4 is also incorrect because this is not an example of a functional structure.