Question 50
What are the three common types of project constraints?
- A Time, cost, and quality
- B Budget,schedule, and scope
- C Requirements, stakeholders, and deliverables
- D Resources, risks, and objectives
Reveal correct answer
Correct answer: A
Explanation
Project constraints are factors that limit or restrict the options available to a project manager in achieving the project objectives. The three common types of project constraints are time, cost, and quality. Time constraint refers to the project deadline and the available time frame for completion. Cost constraint refers to the budget allocated for the project. Quality constraint refers to the level of quality that is required to meet the project objectives and satisfy the stakeholders' needs. These constraints are often interdependent and trade-off decisions need to be made in order to balance these constraints and deliver a successful project. PMFCC38Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.