Certified Associate In Project Management CAPM · Free Practice Question Easy
Question 37
Recently, the development firm Allie works for, as a project manager, was sold to new management, and the transition between the administration has been challenging. As Allie prepares for an upcoming project, she wishes to address some internal strategic and political issues that may affect her project team. Of the following choices, which is the best choice for Allie to speak with regarding her concerns?
- A The project sponsor
- B All of the stakeholders
- C The project business analyst
- D The project management office
Reveal correct answer
Correct answer: A
Explanation
The project sponsor is usually the high-level advocate for the project. The project sponsor approves the funding and will have insight into the strategic and political issues that may affect a project. Not all stakeholders are responsible for the political nuances and strategy of a company. The PMO establishes processes, policies, and procedures for projects but does not affect the political and strategic issues related to the project. The project business analyst focuses on the requirements of the project, which is tactical. RPM3.1.174Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.