Certified Associate In Project Management CAPM · Free Practice Question Easy

Question 12

A photography studio is creating a traveling set made from a vintage Airstream trailer. The trailer will house backdrops, costumes and props, and a makeup station to make on-location photoshoots easier for everyone involved. Antonio is working alongside the staff at the studio to understand best what will be and what will not be included in this project. From this description, what project management process is Antonio performing?
  • A Plan scope management
  • B Formal acceptance documents
  • C Project documentation management
  • D Project change control
Reveal correct answer

Correct answer: A

Explanation

Antonio is performing the plan scope management process. The plan scope management process defines and controls what is and what is not included in the project. Project documentation management and project change control are procedures to allow the control of changes to the project scope only. The formal acceptance documents are part of the close project or phase process. PSM5.1.46

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.