Certified Associate In Project Management CAPM · Free Practice Question Easy
Question 9
Which of the following is not an output of the perform qualitative risk analysis process?
- A Risk register
- B Risk report
- C Risk management plan
- D Issue log
Reveal correct answer
Correct answer: C
Explanation
The risk management plan is an input — not an output — to the perform qualitative risk analysis process. The issue log is an output of the perform qualitative risk analysis process (included in the project documents updates). The risk report is an output of the perform qualitative risk analysis process (included in the project documents updates). The risk register is an output of the perform qualitative risk analysis process (included in the project documents updates). PRM11.2.126Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.