Certified Associate In Project Management CAPM · Free Practice Question Easy
Question 5
Which of the following is NOT an activity typically associated within a predictive, plan-based methodology of project management?
- A Performing backlog grooming
- B Defining project scope
- C Conducting a risk assessment
- D Creating a detailed project schedule
Reveal correct answer
Correct answer: A
Explanation
Performing backlog grooming is NOT typically associated with a predictive, plan-based methodology. A predictive, plan-based methodology of project management involves defining the project scope, creating a detailed project schedule and conducting a risk assessment. These activities help establish a clear plan for how the project will be executed and managed. Backlog grooming is an agile methodology, and while it may be used in conjunction with PPBM it is not typically considered part of it. PPBM5Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.