Which of the following is NOT an activity typically associated within a predictive, plan-based methodology of project management?
  • A Performing backlog grooming
  • B Defining project scope
  • C Conducting a risk assessment
  • D Creating a detailed project schedule
Reveal correct answer

Correct answer: A

Explanation

Performing backlog grooming is NOT typically associated with a predictive, plan-based methodology. A predictive, plan-based methodology of project management involves defining the project scope, creating a detailed project schedule and conducting a risk assessment. These activities help establish a clear plan for how the project will be executed and managed. Backlog grooming is an agile methodology, and while it may be used in conjunction with PPBM it is not typically considered part of it. PPBM5

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need