Question 35

Which of the following is NOT a responsibility of testers involved in iteration planning?

  • A

    Participating in the detailed risk analysis of user stories

  • B

    Determining the testability of user stories

  • C

    Breaking down user stories into tasks, particularly testing tasks

  • D

    Estimate test effort associated with user stories

Reveal correct answer

Correct answer: D