Certified Business Analysis Professional CBAP · Free Practice Question Medium
Question 21
In a software development project, the marketing team prioritizes features that enhance customer engagement, while the operations team focuses on features that improve system efficiency. You need to elicit requirements from both groups of stakeholders and run a holistic prioritization of the requirements. Based on this input, what can you anticipate about the upcoming prioritization session, where representatives from both teams will be present?
- A Solution will need to be re-designed
- B Many requirements will be prioritized as low priority
- C Conflicts may occur
- D Unbiased prioritization will happen
Reveal correct answer
Correct answer: C
Explanation
Prioritization is an assessment of relative value. Each stakeholder may value something different. When this occurs, there may be conflict amongst stakeholders. BABOK 5.3 Prioritize RequirementsDiscussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.