SAFE Release Train Engineer RTE · Free Practice Question Medium

Question 16

At which stage of an Inspect and Adapt (I&A) Event are the variations between the planned business value and the actual business value presented?
  • A PI System Demo
  • B Retrospective
  • C Quantitative and qualitative measurement
  • D Problem-solving workshop
Reveal correct answer

Correct answer: C

Explanation

The Inspect and Adapt (I&A) Event consists of three parts:

  1. PI System Demo

  2. Quantitative and qualitative measurement

  3. Retrospective and problem-solving workshop


In the second part, Teams collectively review any quantitative and qualitative metrics they have agreed to collect, then discuss the data and trends.


Each Team's planned and actual business value is rolled up to create the ART predictability measure.


Study Guide: Here's the SAFe 6.0 article with the complete explanation: https://scaledagileframework.com/inspect-and-adapt/

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need