SAFE Release Train Engineer RTE · Free Practice Question Easy

Question 5

What key activity occurs during the first team breakout session in PI Planning?

  • A Teams use color coding for their backlog items to remind them that they must have all the item types on their planning boards
  • B All teams' planning boards are visible and used the same color-coding
  • C Draft objectives are written but do not include exploration Enablers
  • D Risks on the teams' planning boards are resolved by the Release Train Engineer (RTE)
Reveal correct answer

Correct answer: B

Explanation

During PI (Program Increment) Planning, which is a key event in the Scaled Agile Framework (SAFe), multiple Agile teams come together to plan and coordinate their work for the upcoming Program Increment. During the first team breakout session, each Agile team works on its own planning board. The planning board typically consists of a physical or virtual space where teams visualize their work and plan their activities for the Program Increment. The purpose of the planning board is to provide a shared visual representation of the team's planned work, progress, and dependencies. To ensure effective collaboration and alignment across teams, it is important that all teams' planning boards are visible to everyone and use the same color-coding system. This allows for better transparency and understanding among teams, making it easier to identify dependencies, track progress, and coordinate efforts. By using consistent color-coding, teams can communicate and share information more efficiently during the breakout session and throughout the PI Planning event.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need