Your project implementation plan defines 12 capabilities of the planned systems solution that will not be needed once the new solution is operational. What type of requirements are these?
- A Transition requirements
- B Nonfunctional requirements
- C Reusable requirements
- D Functional requirements
Reveal correct answer
Correct answer: A
Explanation
Transition requirements describe the capabilities needed to transition from the current state to the future state. They are temporary and not needed once the transition is complete.Discussion