Question 11

A business analyst is tasked with maintaining requirements for an ongoing project to enhance a customer portal. How can the BA ensure that any changes to the requirements are properly managed?
  • A Implement a formal change control process.
  • B Document all changes in a personal log.
  • C Communicate changes informally during team meetings.
  • D Wait for the project manager to approve all changes
Reveal correct answer

Correct answer: A

Explanation

Implementing a formal change control process for requirements updates ensures that changes are properly managed, documented, and approved. This process helps maintain consistency and traceability.