Professional Scrum Master Ii PSM Ii · Free Practice Question Easy
Question 14
A Scrum team has been formed and the Technical leader has left on holiday while being in the middle of a Sprint. During his absence, who is responsible for managing the tasks of the Sprint? (Choose the best answer)
- A The Scrum Master.
- B The Developers.
- C The Team Leader
- D The Product Owner.
- E The Project Manager.
Reveal correct answer
Correct answer: B
Explanation
During the Technical leader's absence, the Developers should collectively manage the tasks of the Sprint. In Scrum, the team is self-organizing and cross-functional, meaning each member is capable of taking on various responsibilities to ensure the Sprint progresses smoothly. Without the Technical leader, the Developers collaborate to distribute tasks, address any impediments, and ensure that the Sprint's goals are being pursued effectively. The Scrum Master also plays a role in facilitating the team's self-organization and can step in to assist if needed.Discussion
Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.
You must be logged in to post a comment.
