Professional Scrum Master Ii PSM Ii · Free Practice Question Medium
Question 13
Paul, a Product Owner from one of the Scrum teams, has been attending the Daily Scrum. During the Daily Scrum, the Developers have been reporting their daily work to Paul so that he is aware of their Sprint progress and what each member is working on. What is the best action for the Scrum Master to take? (Choose the best answer)
- A Ask Paul to stop attending the Daily Scrum.
- B Allow Paul to participate in the Daily Scrum as he is responsible for the product's success.
- C Facilitate the Daily Scrums to avoid any conflicts between the Developers and Paul.
- D Coach Paul and the Developers on the purpose of the Scrum events and let them figure out what to do in this situation.
Reveal correct answer
Correct answer: D
Explanation
Because the Developers are the ones doing the work, they are best suited to inspect and adapt the progress toward the Sprint Goal. At a minimum, this is done every 24 hours through the Daily Scrum. It is the Scrum Master’s responsibility to teach the Scrum team the value and objective of each Scrum event for them to optimize the benefits of each event. Because the Daily Scrum is owned by the Developers, it is up to them on how they should run it. However, the Scrum Master can provide guidance to ensure it adheres to the Scrum guidelines.Discussion