Professional Scrum Product Owner I PSPO I · Free Practice Question Easy
Question 93
During the Sprint, who is responsible for deciding how work is carried out?
(choose the best answer)
- A The Developers
- B The entire Scrum Team
- C The Scrum Master.
- D The team's manager
- E Experts in the subject matter
Reveal correct answer
Correct answer: A
Explanation
According to the Scrum Guide, the Developers are responsible for organizing and managing their own work during the Sprint. They are self-managing, which means they have the autonomy to decide how to best accomplish their work, rather than being directed by others outside the team.Discussion