Professional Scrum Product Owner I PSPO I · Free Practice Question Easy

Question 93

During the Sprint, who is responsible for deciding how work is carried out?

(choose the best answer)

  • A The Developers
  • B The entire Scrum Team
  • C The Scrum Master.
  • D The team's manager
  • E Experts in the subject matter
Reveal correct answer

Correct answer: A

Explanation

According to the Scrum Guide, the Developers are responsible for organizing and managing their own work during the Sprint. They are self-managing, which means they have the autonomy to decide how to best accomplish their work, rather than being directed by others outside the team.