Professional Scrum Product Owner I PSPO I · Free Practice Question Easy
Question 91
In Scrum, when should a new Increment be available for inspection?
(choose the best answer)
- A Before each planned release
- B By the end of each Sprint, before the Sprint Review
- C Every 2 Sprints
- D Whenever the user acceptance testing is complete
- E When the Scrum Master or the Product Owner asks for it
Reveal correct answer
Correct answer: B
Explanation
According to Scrum, a new Increment of the product must be available by the end of each Sprint, before the Sprint Review. This allows stakeholders to inspect the product's progress and provide feedback.Discussion