Question 79
What is the duration of the gap between the conclusion of one Sprint and the commencement of the next Sprint?
(choose the best answer)
- A There's a one-week hiatus after a four-week Sprint, and typically shorter for briefer Sprints.
- B Just enough time to define and document the necessities for the upcoming Sprint.
- C A duration required for the Developers to wrap up the testing from the preceding Sprint.
- D Zero. A new Sprint starts immediately following the end of the previous Sprint.
- E Any of the listed options might be valid, contingent on the context.
Reveal correct answer
Correct answer: D
Explanation
In Scrum, there is no downtime between Sprints. As soon as one Sprint ends, the next Sprint begins immediately. This ensures a continuous flow of development and maximizes the efficiency and productivity of the Scrum Team.Discussion