Question 74

True or False: Depending on the circumstances, the Product Owner has a say in scheduling and budgeting decisions. Regardless, the Product Owner should review the timelines and budget, typically, at least once a Sprint.
  • A TRUE
  • B FALSE
Reveal correct answer

Correct answer: A

Explanation

Since the Product Owner is accountable for product decisions and value maximization, he/she should review the timelines and budget to ensure alignment with stakeholders and that the goals are met. Further, regular review of timelines and budget aligns with the principles of transparency and inspection, enabling the Product Owner to make informed decisions