Professional Scrum Product Owner I PSPO I · Free Practice Question Medium

Question 70

Which two statements best describe the Product Backlog?

(Select the best two answers)

  • A It changes as we learn more about the product.
  • B Contains all tasks identified by the Developers.
  • C It's used to create the project plan.
  • D The Product Owner is accountable for it.
Reveal correct answers

Correct answers: A, D

Explanation

"Contains all tasks identified by the Developers".

- Tasks are identified in the Sprint Planning meeting or during the Sprint, and are captured only in the Sprint Backlog.


"It's used to create the project plan".

- There's no "project plan" in Scrum. Product Backlog is the closest thing to a project plan that we have in Scrum.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.