Professional Scrum Product Owner I PSPO I · Free Practice Question Medium

Question 67

True or False: During Sprint Retrospective the definition of Done can not be reviewed and adapted.
  • A TRUE
  • B FALSE
Reveal correct answer

Correct answer: B

Explanation

The Scrum Team inspects how the last Sprint went with regards to individuals, interactions, processes, tools, and their Definition of Done.