Professional Scrum Product Owner I PSPO I · Free Practice Question Easy

Question 62

When does a subsequent Sprint commence?

(choose the best answer)

  • A Once the items for the next Sprint have been identified from the Product Backlog.
  • B After the main design changes for the upcoming Sprint receive a nod from the lead designer.
  • C Once the client finishes their review of the prior Sprint's outcome.
  • D After the Sprint Retrospective is over.
Reveal correct answer

Correct answer: D

Explanation

The Sprint Retrospective concludes the Sprint. The Scrum Guide emphasizes that Sprints are continuous, with one Sprint following the other. There is no gap between Sprints; when one ends, the next begins. This ensures a continuous flow of delivery and feedback.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need