Professional Scrum Product Owner I PSPO I · Free Practice Question Easy
Question 32
Who is responsible for managing the Sprint Backlog?
(choose the best answer)
- A The Scrum Master.
- B The Scrum Team.
- C The Product Owner.
- D The Developers.
Reveal correct answer
Correct answer: D
Explanation
According to the Scrum Guide, the Sprint Backlog is owned and managed by the Developers. It is a plan for how the team will achieve the Sprint Goal and deliver a "Done" Increment. The Developers are responsible for updating the Sprint Backlog daily to reflect the remaining work and for ensuring that it provides a clear picture of their progress towards the Sprint Goal. While other members of the Scrum Team, such as the Product Owner and Scrum Master, may provide input and guidance, ultimately, it is up to the Developers to manage their own work within the Sprints.Discussion