Professional Scrum Product Owner I PSPO I · Free Practice Question Easy

Question 30

True or False: The Product Owner is accountable for maximizing the product's value.
  • A TRUE
  • B FALSE
Reveal correct answer

Correct answer: A

Explanation

This is true as per the Scrum Guide. The Product Owner is accountable for ensuring that the developed product delivers the maximum value.