Professional Scrum Product Owner I PSPO I · Free Practice Question Medium

Question 14

What is the accountability of management in relation to a Scrum Team?

(choose the best answer)

  • A To identify and dismiss team members who are not performing well.
  • B Management is responsible for creating an environment that supports the self-managing and empowerment of the Scrum Team, such as providing resources and insights to help them improve.
  • C To assign tasks to the Developers.
  • D To constantly monitor the staffing levels of the Scrum Team.
Reveal correct answer

Correct answer: B

Explanation

In Scrum, the accountability of management in relation to a Scrum Team is to create an environment that enables the team to self-manage and be empowered. This means that management should provide the necessary resources, support, and insights to help the team succeed. Instead of assigning tasks to the Developers or tracking their productivity, management focuses on enabling the team to take ownership of their work and make decisions collectively. By fostering a culture of trust and collaboration, management facilitates the team's ability to deliver value and continuously improve. Monitoring staffing levels is not the primary accountability of management in Scrum, as the team is responsible for self-managing and determining the most effective way to accomplish their work.

Discussion

Think the marked answer is wrong, or have a better explanation? Share it below — comments appear after review.

You must be logged in to post a comment.

Preparing For

Your Certification?

255+ certifications
Detailed explanations
Free PDF samples

Has All The Questions You Need